Shuttering

The current focus is on preparing for the concreting in of the steelwork for the new treble.


The shuttering has been cut and fixed in place complete with a slot where the concrete can be inserted.

The shuttering now needs sealing with expanding foam and the hard work of mixing and hauling up buckets of concrete can begin.
Posted by David Bagley at 22:39 No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Newer Posts Older Posts Home
Subscribe to: Posts (Atom)

Total Pageviews

Blog Archive

  • ►  2021 (13)
    • ►  December (1)
    • ►  October (1)
    • ►  September (2)
    • ►  August (3)
    • ►  July (2)
    • ►  June (1)
    • ►  April (2)
    • ►  February (1)
  • ►  2020 (9)
    • ►  September (1)
    • ►  May (1)
    • ►  April (1)
    • ►  March (2)
    • ►  February (1)
    • ►  January (3)
  • ►  2019 (24)
    • ►  December (3)
    • ►  November (7)
    • ►  October (4)
    • ►  September (3)
    • ►  August (1)
    • ►  July (1)
    • ►  June (1)
    • ►  March (1)
    • ►  February (1)
    • ►  January (2)
  • ▼  2018 (14)
    • ►  December (1)
    • ►  November (4)
    • ▼  September (1)
      • Shuttering
    • ►  August (1)
    • ►  July (2)
    • ►  May (2)
    • ►  March (1)
    • ►  February (1)
    • ►  January (1)
  • ►  2017 (21)
    • ►  December (2)
    • ►  November (2)
    • ►  October (1)
    • ►  September (5)
    • ►  August (1)
    • ►  July (3)
    • ►  June (3)
    • ►  May (2)
    • ►  April (2)
Simple theme. Powered by Blogger.